SuDS Maintenance

A contractor will be on site carrying out essential maintenance works to the Great Parks Sustainable Urban Drainage Systems (SuDS). The works to be undertaken during February and will last approx. 5 weeks with an indicative programme set out below.

  • Elmwood Park Gardens (Cell C) pond will be flailed, silt removed and stored on the bankside which will take around 5 days.
  • Warkworth Woods (Cell H) pond will be flailed, silt removed and stored on the bankside which will take around 3 days.
  • Melbury (Cell I) pond will be flailed, silt removed and stored on the bankside which will take around 5 days.
  • Greenside (Cell G) pond will be flailed, silt removed and stored on the bankside which will take around 5 days.
  • Town Centre, East Moor Village & Brunton Grange (Cell F) pond will be flailed, silt removed and stored on the bankside which will take around 5 days.
  • Proposed fencing will then be erected taking around 5 days.

Newcastle Great Park Management Company